Question 1

The Lean Principle action in the 5S approach that deals with having those items needed regularly at hand and those items need less regularly stored out of the way is known as ___________.


  1. Shining
  2. Standardizing
  3. Sustaining
  4. Sorting
Correct answer: D



Question 2

SPC on the outputs is more preferred than SPC on the inputs when implementing SPC for your process. 


  1. True
  2. False
Correct answer: B



Question 3

Significant variation in process performance is a consequence of several causes that can be classified using which of the terminologies shown. (Note: There are 2 correct answers).


  1. Common
  2. Random
  3. Uneducated
  4. Special
  5. Vital
Correct answer: AD



Question 4

When it comes to Control one of the most effective means of eliminating defects is to _________________ .


  1. Train personnel often and thoroughly
  2. Keep a Six Sigma project going on the process at all times
  3. Design defect prevention into the product
  4. Have each process consist of no more than five steps
Correct answer: C



Question 5

If a process has Outliers which pair of charts is most preferable if subgroups will exist for the Continuous Data?


  1. Individual—Moving Range
  2. Xbar-R Charts
  3. Xbar-S Charts
  4. nP and P Charts 
Correct answer: B



Question 6

After a Belt has put data through the smoothing process which chart would be used to look for trends in the data?


  1. Moving Average Chart
  2. Multi-Vari Chart
  3. X bar Chart
  4. Pareto Chart
Correct answer: A



Question 7

A Belt concludes a Lean Six Sigma project with the creation of a Control Plan. At what point can the Control Plan be closed?


  1. Never, a Control Plan is a living document
  2. As soon as the Champion signs off
  3. Within 30 days of the LSS project review team meeting
  4. After the project has been presented at the recognition event
Correct answer: A



Question 8

When analyzing a data set we frequently graph one metric as a function of another. If the slope of the Correlation line is -2.5 we would say the two metrics are ___________ correlated?


  1. Positively
  2. Not
  3. Negatively
  4. None
Correct answer: C



Question 9

Multiple Linear Regressions (MLR) is best used when which of these are applicable? (Note: There are 3 correct answers). 


  1. Non-linear relationships between the inputs X’s and output Y
  2. Uncertainty in the slope of the linear relationship between an X and a Y
  3. Relationships between Y (output) and more than one X (Input)
  4. Preventing the use of a Designed Experiment if unnecessary
  5. We assume that the X’s are independent of each other
Correct answer: CDE
Explanation:



Question 10

Fractional Factorial designs for an experimental approach are used when ____________ about the multiple metric interaction in a process.


  1. Much is known
  2. Little is known
  3. We don’t care
  4. Data exists
Correct answer: B